First tests of HYFOR performed at the pilot plant at the voestalpine site in Donawitz

Categories: |
Topics: | | | | | |
Author: Editorial Office

First tests of HYFOR performed at the pilot plant at the voestalpine site in Donawitz
Photo of the HYFOR direct reduction pilot plant for iron ore fines developed by Primetals and located at the voestalpine site in Donawitz. Photo: Primetals Technologies

24.06.2021. In April, the hydrogen-based fine-ore reduction (HYFOR) pilot plant developed by Primetals Technologies was commissioned at the voestalpine site in Donawitz, Austria. First tests were successful. Test with various iron ore concentrates will continue to collect a sound data basis.

100 % hydrogen as reduction agent

Use of 100 % hydrogen as reduction agent reduces the CO2 footprint close to zero. The HYFOR pilot plant employs the world´s first direct reduction process for iron ore fines concentrates from ore beneficiation, not requiring any agglomeration like sintering or pelletising. This reduces CAPEX and OPEX costs. HYFOR represents the only process worldwide capable of processing iron ore concentrate fines with 100 % particle sizes smaller than 0.15 mm, and a wide variety of ores, e.g. hematite and magnetite, supplied by different customers of Primetals worldwide. The direct reduction plant will come in a modular design, allowing for a tailor-made scaling for customers for all sizes of steel plants.

First tests have been successfully executed in April and May 2021 The scale of one test run is in the range of processing of 800 kg iron ore. The pilot plant shall be operated for at least two years in multiple campaigns to test various ore types and to evaluate the optimal process parameters for the next scale up step. Smooth operation assumed, a hot briquetting unit will be added to verify the hot briquetting step as well as the HBI quality to be expected from the HYFOR technology.

First direct reduction process for iron ore concentrates not requiring any agglomeration like sintering or pelletising

Primetals has developed the world´s first direct reduction process for iron ore concentrates not requiring any agglomeration like sintering or pelletising. Primetals can resort to the comprehensive experience from the earlier Finmet/FINORED and FINEX development and plant installations. The new technology can be applied to all ore types (hematite and magnetite) and particle sizes of up to 100 % smaller than 0.15 mm. As primary reduction agent, the new process uses 100 % hydrogen from renewable energy or alternatively H2-rich gases from other gas sources like natural gas pyrolysis or conventional steam reformers. This results in a low or even a zero CO2 footprint. The direct reduction plant will come in a modular design, making it available for all sizes of steel plants. The product is hot DRI for direct hot transport and feed to the downstream melting like EAF or Hot Briquetted Iron (HBI) for being sold to the market.

The use of DRI/HBI is expected to continue to grow due to the need to the strong demand to decarbonise the steel sector and the growing number of electric arc furnaces in service worldwide. Currently, all available technologies require agglomeration, like pelletising to produce DRI or HBI. An additional challenge steel producers face, is the reduced quality of iron ore, resulting in the need to beneficiate the iron ores. In order to progress to a CO2-free steel production, a process using mainly H2 is most desirable. The new HYFOR process developed by Primetals takes care of all the above considerations.

Pilot plant

The pilot plant consists of three parts: a preheating-oxidation unit, a gas treatment plant and the actual reduction unit. In the preheating-oxidation unit, fine ore concentrate is heated to approx. 900 °C and fed to the reduction unit. The reduction gas, 100 % H2, is supplied over the fence from a gas supplier. A dry dedusting system takes care of dust recycling to prevent emissions from the processes involved. The hot direct reduced iron (HDRI) leaves the reduction unit at a temperature of approx. 600 °C before its cooled down and discharged from the pilot plant. The next step will be the addition of a Hot Briquetting Testing facility to produce Hot Briquetted Iron (HBI).

The aim of the HYFOR pilot plant is to verify this break-through process and to serve as a testing facility to provide the data basis for upscaling the plant size to an industrial-scale prototype plant as the next development step.

This project is funded by the Climate and Energy Fund and is carried out under the program “Energieforschung”. For further information: www.klimafonds.gv.at and www.energieforschung.at

 

(Source: Primetals Technologies)